Wastewater
Sohag Airport SWTP
Power and control panel installation, programming and commissioning with SCADA support for a 300 M3/day sewage treatment plant.
SWTP Control and SCADA
Automation Scope
System Components
Power and control panel
SCADA process screens
PLC programming
Site wiring and commissioning
Scope of Work
Control panel installation and wiring support
PLC programming and SCADA screen setup
Process screens for tanks, pumps, filters and blowers
Commissioning support and final system checks
Project Gallery
Operator Screens, Panels and Process Details





Project Outcome
The completed wastewater treatment automation package provides coordinated PLC and SCADA control, clear process monitoring, and reliable support for commissioning and day-to-day plant operation.